Payab Gheshlagh's Main Conveyance Canal - Sanandaj

Including :procurement of all construction equipment and construction , installing,Analayzing

and Implement of the Gheshlagh payab main conveyance canal and making of hydro

mechanical equipment related to flow control system and training the operation personnel

and procurement of the As-Built drawings and preparing and maintenance and operation

instruction

Major  operation  activities  are :

Excavation-in rock &soil 97,840 Cub.m
Excavation-Canal 37,368 Cub.m
Form  Work 72,469 Sq.m
Bar  Work 1,065Ton
Concrete work 17,676  Cub.m
Construction of Administrative & Residential & Back up 728 Sq.m