Including implemeting and excavation and lining of the two Tunnel , each 500 meter long and two vertical and one angled shaft ( total length:120 meter) and their subordinate structures in beginning along and at the end of the part and also Pre-Constructing the camp and landscaping of the camp
Major operation activities are :
Excavation | 138,754 Cub.m |
Embankment | 67,312 Cub.m |
Drilling work (Tunnel & Shaft ) | 39,595 Cub.m |
Bar Work | 445 Ton |
Concrete Work | 13,694 Cub.m |
Construction of Administrative & Residential & backup buildings | 1,926 Sq.m |