Including :implementing and construction of the Aidoghmoosh irrigation and drainage network included conveyance tunnel and canal.
Project is located in Aidoghmoosh area -south of the Miyaneh city.
Detials are mentioned below:
1- Construction of the canal (ave. length : 6.7 Km)
2- Construction of one unit of tunnel ( ave. length : 2.28 Km)
3- Construction of two unit of tunnel ( ave. length of each one: 560 m)
4- Construction of the technical buildings related to canal .
5- Construction of the canal service roads (ave.of total length : 6.7 Km)
Major operation activities are :
Excavation-in rock | 879,000 Cub.m |
Excavation-Canal in rock | 147,800 Cub.m |
Tunnel drilling | 73,155Cub.m |
Steel frames for tunnel | 74 ton |
Form Work (canal) | 69,180 Sq.m |
Form Work (tunnel) | 15,697Sq.m |
Bar Work | 3,590 ton |
Concrete work (canal) | 22,361 Cub.m |
Concrete work (tunnel ) | 20,993 Cub.m |
Shotcrete | 80,842 Sq.m |