Constructing the Interchange Bridges No .2 , 3 and retaining walls zone No . 4 - Abas Abad field
Major operation activities are :
| Excavation | 97,648 Cub.m |
| Embankment | 3,955Cub.m |
| Form Work | 19,786Sq.m |
| Bar Work | 1,380Ton |
| Heavy Steel Work | 72Ton |
| Concrete Work | 12,434Cub.m |