Construction of the fifth segment of Khajeh-Varzaghan-Aghbaba’s highway

Khajeh-Varzaghan-Aghbaba’s section five highway (from kilometers 50+200 to 61+550) is located in east Azerbaijan province. This project is approximately 11350 meters long, with the final width of 15 meters. It includes 11 meters of asphalted roads and two gravel road sides, each with the width of 2 meters. Infrastructure, base, asphalting, and technical building operations are as follows:

1-Road’s earth work, infrastructure, base, and asphalting operations, including all necessary works to complete its infrastructure and pavement

2-Cunstructing culvert valleys in the kilometers of 58+148, including two craters that each are six meters’ long

3-Construction of Varzaghan-Casin’s rural underpass in kilometers of 55+455 including an 8 meters’ carter

4-Bridge construction with the Aharchaie’s confluence in the kilometers of 54+980 including three culverts that each are 10 meters’ long

5-Construction of an underpass with the Varzaghan-GovinjehSoltan’s confluence in the kilometers of 50+531, including an 8 meters’ culvert

Major volumes of the project operations are as follows:

Excavation Work 1,531,000 Cub.m
Embankment 958,400 Cub.m
Concrete Forming 32,681 Sqr.m
Concrete Pouring 22,211 Cub.m
Rebar Tying 738 Ton
Base Course 50,564 Cub.m
Prime Coat 106,099 Kg
Asphalt Binder 1,822,356 Sqr.m-Cm
Asphalt Surface 1,512,387 Sqr.m-Cm